Major Achievements of TRD/ECR for the period from FY-2022-23.

1)Electrification of 227.762 RKM & 608.588 TKM has been completed in F.Y. 2022-23 as compared to 209.141 RKM & 447.923 TKM in F.Y. 2021-22.

2)06 Nos. new Traction Sub-stations (TSSs at NNA, TIA, RXL, HPO, BGU & XBKJ) have been commissioned in F.Y. 2022-23 as compared to 03 Nos. Traction Sub-stations (TSSs at BRHI, NUQ & BJT) commissioned in F.Y. 2021-22.

3)10 Nos. SP/SSP have been commissioned in F.Y.2022-23 as compared to 05 Nos. SP/SSP commissioned in F.Y. 2021-22.

4)Electrification of total 49.780 TKM of Sidings have been completed in F.Y. 2022-23 as compared to 33.678 TKM in F.Y. 2021-22.

5)TRD asset failures have reduced to 460 nos during F.Y. 2022-23 as compared to 489 cases during F.Y. 2021-22, thereby achieving 5.93% improvement.

6)An amount of Rs. 41.989 Crores (Prov.) is saved by availing power at cheaper rate through Open Access during F.Y. 2022-23 (upto Nov’22).

Electrification Achievement

2021-22

S.N.

Section

RKM

1

Sitamarhi - Raxaul

79.310

2

Saharsa - Garhbaruari

16.103

3

Dauram Madhepura - Banmankhi

43.368

4

Ghoswar - Vaishali

30.220

5

Raxaul - Narkatiaganj

40.140

Total RKM

209.141

 

 

2022-23

1

Banmankhi – Purnia

33.204

2

Barkakana – Sanki

31.128

3

Sakri Tamuria

28.97

4

Banmankhi - Bihariganj

27.3

5

Narkatiaganj - Amolwa

13

6

Hasanpur - Bithan

12

7

Saraygarh – Garbahbaruari

35.5

8

Saraygarh – Raghopur

10.97

9

Sakri - Biraul

35.69

 

Total RKM

227.762


INNOVATION – SMART OHE

ALL PARAMETERS OF OHE ARE MAINTAINED AS PER ACTM (AC TRACTION MANNUAL) AND RDSO GUIDELINE. INNOVATIVE MAINTENANCE STRATEGY BASED ON LATEST TECHNOLOGY ARE BEING ADOPTED FOR BETTER MAINTENANCE STRATEGY, REDUCED FAILURES,, SPEED,EFFICIENCY & ECONOMY . TO MAKE OHE SMART AND ECONOMIC, SYSTEM LIKE TDMS, TEMS,OPEN ACCESS, TRACKSIDE SOLAR AND 2x25 KV SYSTEM etc ARE BEING INTRODUCED BY ELECTRICAL DEPARTMENT.

TRACTION DISTRIBUTION MANAGEMENT SYSTEM (TDMS App)

GPS based tracking of Patrol man and OHE assets.

Real time capturing of OHE defects and provision of taking photographs.

Exception generation and alerts through SMS to depot in-charge and officers.

Efficient analysis and decision making through real time reporting and images.

TDMS- INNOVATIVE MAINTENANCE STRATEGY

 

Existing System

Foot patrolling by TRD staff/ supervisor for capturing defects in OHE.

Entry of defects in foot patrolling form and register.

Expectation

Real time defects capturing.

Tracking of foot patrolmen.

Digitalformandreport generation.

Categorization of defects for better understanding.

 

 

 

 

TDMS APPLICATION FOR FOOT PATROLMEN

Need for an software/application for Patrolling activity

 

 

 

 

MONITORINGTHROUGH TDMS

Masters- 44 Point Reliability Action Plan.

Reports-

Inspection register- (i) OHE Breakdown (ii) One Page Report

Asset Register- Cantilever Assembly, Catenary wire , Contact wire, Earth Resistance, HT crossing, Isolator Switch, Jumper, Level Crossing Gauge, Mast/Portal, OHE Gantry, Over line Structure, Overlap, PTFE, Regulating Equipment, Section Insulators, Turn Out X-over.

Asset Maintenance Register- Details of items as per Asset Register.

Daily Progress Register-Daily progress report should be upload on TDMS by Depot In charge (SSE) of Divisions.

Master Defects Register-Defects should be entered in format –

        (I) Location (ii) Asset Type  (iii) Items needing attention (iv) Defective value/condition (v) Compliance date (vi) Compliance by

Thermography Report-OHE/PSI components are checked by Thermal Vision Camera for its healthiness.

Asset status Report-This report is up load by In charge of Depots/SSE.

Maintenance due overdue Report-

Foot Patrol Report- Foot patrolling is done with mobile app.

Current Collection Report- Current Collection is conducted by OLIVIR G.


ADVANTAGES OF TDMS

Great app - quite a need especially due to covid-19

Patrolling monitoring and issue logging simplified.

Audit & Tracking of reported issues streamlined.

Faster resolution of issue with available data and images.

    •Performance reporting.

 

TRACTION ENERGY MANAGEMENT SYSTEM (TEMS)

▪ Availing Open Access &migrating from consumer mode.

▪ Close Load Scheduling of TSSs for open access.

▪Aggregation of Instantaneous and block-wise load profiles.

▪Report generation for -analysis -improved forecasting and scheduling of load.

▪Comparison of actual drawl against scheduled drawl.

▪Load schedule violation prediction alarm generation when schedule violates.

▪Real-time monitoring of TSS’s Energy & Line parameters.

▪Data visualization and report generation.

▪Alarm generation when meter parameter’s limit violates.

GREEN & LOW COST POWER FOR OHE

Ø Installation of Solar Panel along the track (5 m apart from track), produced power will be feed to OHE. Survey of Land for Installation of Solar Panel is under progress.

Solar power will be feed to OHE through Power Banking System.

 Advantage  Of Installation of Solar Pane  

This will reduce energy cost.

Green Energy, suitable for environment.

Use of un- utilized land.

 

 

Open Access in E C Railway

In terms of Electricity Act, 2003 , Power for Traction is availed through Open Access as it provides Non-discriminatory sale/purchase of electric power/energy between two parties utilizing the system of an in-between (third party), and not blocking it on unreasonable grounds.

To ensure consumers receive adequate supply from alternate competitive sources and enabling the captive generators to sell their surplus capacities while the distribution licensee improves performance.

Railways as deemed distribution licensee taking power from generators for zonal railway from BRBCL, RGPPL, JIPTL as follows:

From BRBCL/NTPP : ECR, ECR, ER, SER, NR, NER, NFR, NCR, WCR, CR, WR

From RGPPL : CR, SER

From JIPTL : NR

Open Access with BRBCL :Joint venture of Railway and NTPC

BRBCL is Joint venture of Railway and NTPC for setting up 4x250MW Power Project at Nabinagar, Bihar. In which 90% generated power is utilized by Railway.

East Central Railway is Nodal for BRBCL. All bills regarding BRBCL is raised by firm to ECR and

Distribution powerto Railway as allotted by Railway board:

CR-120 MW

WCR-60 MW

NCR-55 MW

NR-185 MW

SWR-10 MW

DVC Command Area-110 MW

ECR(Bihar)-100 MW

Savings from Open Access

Saving as a result of availing power through Open access/BRBCL-

The Average Cost in Consumer mode = Rs.12.06/Unit

The Average Cost in Open Access mode = Rs.7.22/Unit

Saving in Average Cost = Rs.4.84/Unit

Consumption in Open Access = 187.73 Million Unit

Total saving in Open Access in (April’20 to August’20) = Rs.90.86 Crores

Saving as a result of availing power through Open access/DVC is about Rs 70 crores

2x25 KV OHE

will be introduced on GC (PKA- DDU)for operation of train at high speed i.e. 160 kmph Estimate has been got sanctioned recently, Tender to be invited shortly.

Ø Advantage of 2x25 KV OHE

Abolition ofTractions bonds completely. There will be no need to deputethe TRD staff during maintenance of Track by Machine for safety of bonds

Overcome the problem oflow voltage in section, this will be beneficial to Electric loco having latest Technology.

System is designed forhigh speed i.e. 160 kmph

Return Current through Track will be abolished. This will be advantageousfor S&T department.

Problem of Burning of signal bond at Glued Joint will be solved.

No of TSS/SP and SSP will be reduced.



OHE Modification Work related with 160 KMPH Up gradation

Sl. No

Items

DDU Div.DHN Div.ECR (DDU+DHN)

1

Feeder wire Work on separate mast for Up and Dn line separately (In TKM)

578 TKM404 TKM982 TKM

2

Replacement of ATD for 2400 kgf tension(Nos.)

1500 Nos.680 Nos.2180 Nos.

3

Dropping work (TKM)

450 TKM425 TKM875 TKM

4

Replacement of Masts (TKM)

(i)due to realignment of track by engg.

(ii)due to unsuitability for higher tension

(i) Flattering of curve (i) (a) Flattening of (i) Flattering of

95 TKM curve-200 TKMcurve- 295 TKM

(ii) 3200 nos. mast (b) Ghat section-44 (ii) 7280 nos. mast will change under (*)will replace. work OHE replacement for 2400 (ii) 4080 nos. kgf tension .

(*) AEC of 578 TKM required. In earlier estimate it was not taken

5

Adjustment of T/O and X/O ( Nos)

172 nos.

T/O=207 Nos. X/O=60

439 nos.

6

Replacement of single Pole isolator by double pole (Nos)

221 nos.

106 Nos.

327 nos.

7

Work of AEC and BEC (TKM)

AEC- 578TKM(*) BEC- 578 TKM

425 TKM Each

1003 TKM

(*) AEC of 578 TKM required. In earlier estimate it was not taken

 




Source : East Central Railways / Indian Railways Portal CMS Team Last Reviewed : 10-04-2023  


  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.