Electrical General Services
Major Activities in Electrical General Services
Items | 2019-20 (up to Sept’19) | 2020-21 (up to Sept’20) | Remarks |
Energy Consumption (in MU) | 81.82 | 70.41 | 13.94% reduced |
Energy Bill (in M.Rs.) | 600.83 | 515.06 | 14.27% reduced |
HSD Oil Consumption (in KL) | 549 | 375 | 31.69% reduced |
Provision of Lifts | Out of 34 lifts, 21 lifts have been provided at different stations over ECR. Civil work not started at PNBE-4 Nos, Ara-2 Nos, RJPB-1No.,Gaya-1 No. & DBG-2 Nos. |
Provision of Escalators | Out of 35 Escalators, 26 Escalators have been provided at different stations over ECR. Civil work not started at MFP-2 Nos. & HJP-2 Nos. |
Installation of Solar Plant at Rooftop over ECR
Location | Plant Capacity (in MWp) | Tender finalizing agency | Installed (MW) | Remarks |
ECR (All div) | 0.219 | Departmentally | 0.219 | 0.815 MW Installation work to be installed by Azure Power. |
ECR (All div) PPP mode | 5.79 | M/s Azure power Rooftop (GenCo) Pvt. Ltd.@ 3.98 Rs/unit | 4.97 |
DNR div, PPP mode | 0.5 | M/s real value engg& services, Chhattisgarh @ 5.59 Rs/unit | 0.5 |
SEE div, PPP mode | 0.5 | 0.5 |
Total | 7.009 | | 6.189 |
Installation of Solar Plant at Rooftop over ECR
ECR (All div) | 6.86 | Provision of 6.86 MWp at Rooftop of Railway Service Buildings over ECR, LOA issued to M/s Refex Energy Ltd, Chennai through REMCL on 25.10.19. PPA signed on 13.08.2020. PBG is to be submitted by firm. |
ECR (All div) | Solar Plant installation at unused Vacant Land : 3518.801 Acres land has been finalized by divisions and sent to REMCL with the approval of GM/ECR. |
100% Prepaid Energy meters are yet to be provided for outside connections:
Division | Total Outside Connections | Provided | Balance |
DHN | 257 | 216 | 41 |
DDU | 214 | 167 | 47 |
SPJ | 280 | 230 | 50 |
TOTAL | 751 | 613 | 138 |